Project Description

CT Scanner

•  Removal of temporary CT Scanning Unit  •  Part demolition and removal of selected block work planters
•  Excavation of pits and the formation of reinforced concrete pads to accommodate a steel frame for the relocatable CT unit
•  Excavation of pits and the formation of reinforced concrete pads to accommodate a crane pad required to lift the CT unit into position
•  Installation steel frame to accommodate CT unit
•  Installation and commissioning of Relocatable CT unit and associated services
•  Installation and making good of link between CT Scanner unit and Granite Block of the Hospital

PROJECT DETAILS

APPROX. VALUE

£ 180,000.00

CLIENT

Government of Jersey

TIMESCALE

16 weeks